Condition monitoring network — Cement
Wireless vibration and temperature sensors on rotating equipment. Delivered for a cement client in Bhavnagar.
- Location
- Bhavnagar
- Year
- 2021
- Duration
- 24 weeks
- Team
- 12 engineers
- 418
- sensors
- −49%
- unplanned stops
- 3.5 yr
- battery life
The challenge
Existing vendors had delivered pieces of a condition monitoring network system, but nobody owned the integration and the pilot had stalled.
What we built
A phased rollout: a measured pilot first, then scale-out. The core runs on LoRaWAN with ESP32, integrated into existing systems through Grafana.
Delivery timeline
Phase 1
Discovery sprint and site survey
Phase 2
Prototype built and tested in the Motera lab
Phase 3
Pilot on site with before/after measurement
Phase 4
Scale-out, training and handover
Highlights
- Integrated with existing PLC, ERP or GIS systems — no rip-and-replace
- Remote monitoring and over-the-air updates included
- Operator training delivered in Gujarati, Hindi and English
- Runs on-premises; no data leaves the site unless agreed
Related IoT & 5G projects
IoT & 5GPilotTextile · Morbi · 2024
Condition monitoring network — Textile
Wireless vibration and temperature sensors on rotating equipment. Delivered for a textile client in Morbi.
- 1,871
- sensors
- −35%
- unplanned stops
- 2.2 yr
- battery life
IoT & 5GLiveSteel · Motera, Ahmedabad · 2021
Condition monitoring network — Steel
Wireless vibration and temperature sensors on rotating equipment. Delivered for a steel client in Motera, Ahmedabad.
- 2,378
- sensors
- −32%
- unplanned stops
- 4.6 yr
- battery life
IoT & 5GR&DPaper mill · Motera, Ahmedabad · 2024
Condition monitoring network — Paper mill
Wireless vibration and temperature sensors on rotating equipment. Delivered for a paper mill client in Motera, Ahmedabad.
- 2,470
- sensors
- −39%
- unplanned stops
- 4 yr
- battery life
IoT & 5GR&DPharmaceutical · Anand · 2025
Condition monitoring network — Pharmaceutical
Wireless vibration and temperature sensors on rotating equipment. Delivered for a pharmaceutical client in Anand.
- 263
- sensors
- −49%
- unplanned stops
- 4.2 yr
- battery life