Skip to content
RoboticsDeliveredRobotic welding cell

Robotic welding cell — Fabrication

Seam-tracking arc welding for short batches and thin sheet. Delivered for a fabrication client in Hazira.

Location
Hazira
Year
2020
Duration
32 weeks
Team
11 engineers
Interactive 3D · drag to rotate
−65%
rework
3.7 min
programming time
4×
weld speed

The challenge

Existing vendors had delivered pieces of a robotic welding cell system, but nobody owned the integration and the pilot had stalled.

What we built

Built in our Motera lab, validated on a replica rig, then commissioned on site in days using ROS 2 and Modbus.

Delivery timeline

  1. Phase 1

    Discovery sprint and site survey

  2. Phase 2

    Prototype built and tested in the Motera lab

  3. Phase 3

    Pilot on site with before/after measurement

  4. Phase 4

    Scale-out, training and handover

Highlights

  • Documentation, drawings and source handed over at close
  • Runs on-premises; no data leaves the site unless agreed
  • Operator training delivered in Gujarati, Hindi and English
  • Remote monitoring and over-the-air updates included

Have a problem that needs a machine built for it?

Tell us the constraint — line speed, accuracy, environment, deadline. An engineer will read it and reply with a straight answer, including when the answer is that you don't need us.

We reply to every enquiry within one business day.