Discrete-event simulation with a 3D twin for layout what-ifs. Delivered for a fmcg client in Gandhinagar.

Location
Gandhinagar
Year
2024
Duration
30 weeks
Team
13 engineers
Interactive 3D · drag to rotate
−21%
travel distance
268
scenarios run
₹9.1cr
capex avoided

The challenge

Data existed but lived in spreadsheets and legacy systems, so decisions were made on instinct rather than evidence.

What we built

We owned the whole stack — hardware, firmware, models and dashboards — using SimPy, Three.js, glTF so there was one accountable team.

Delivery timeline

  1. Phase 1

    Discovery sprint and site survey

  2. Phase 2

    Prototype built and tested in the Motera lab

  3. Phase 3

    Pilot on site with before/after measurement

  4. Phase 4

    Scale-out, training and handover

Highlights

  • Safety case reviewed with the client's EHS team
  • Operator training delivered in Gujarati, Hindi and English
  • Documentation, drawings and source handed over at close
  • Runs on-premises; no data leaves the site unless agreed